UHT 12 & 13, Nutricia Danone Zoetermeer
Oct 2021 – Oct 2023
- I lead the renovation of multiple story building with a new pipe rack and MCC room. My team of 15 engineers, buyers, maintenance and production liaison is responsible for design, permitting, subcontracting the works, supervision of construction.
- I had to terminate the contract with design firm due their underperformance and hire another engineering company to finish the design.
Dissolving line D4 & D5, Nutricia Danone Zoetermeer
June 2022 – Apr 2024
- I supported the plant manager with feasibility, design, business case and fund approval
- I lead team of designers, architects and contractors to create multiple designs and cost estimates.
- After approval I lead the detail design, tendering, permitting and construction of the building
- Design reviews with Logistics, Process, Safety, Operations and Maintenance
- Before construction could start I lead the pre-project to relocate existing facilities 1000m2.
The construction of the new building started in Feb 23 and was finished on time in April 2024.
- More than 40.000 manhour without LTI